Construction Cost Estimate

EST-2026-0047  ·  Level 2 — ROM  ·  Issued: 2026-06-18
Franklin Agent  ·  Preconstruction Intelligence
Sulphur Springs Public Library — Interior Renovation
Friends of the Library Inc.
611 N. Davis St, Sulphur Springs, TX 75482
June 30, 2026
GMP / Design-Build TI
Public Library — Interior Renovation
28,400 RSF
22 Weeks  (Jul 14 – Dec 12, 2026)
$2,418,300
Subcontracts + Self-perform
$218,500
8.28% of direct
$193,500
7.33% of direct + GC
$144,000
5.0% — Level 2 ROM
$2,974,300
$104.73 / RSF all-in

Division 01 — General Requirements

CSI Code Description Qty Unit Unit Cost Total Conf.
Project Management & Supervision
01-2000 Project Manager (22 wks @ 0.5 FTE) 11 wks $3,850 $42,350 HIGH
01-2010 Field Superintendent (22 wks full-time) 22 wks $4,200 $92,400 HIGH
01-3000 Project Closeout / Commissioning 1 LS $8,500 $8,500 MED
Site Logistics & Temporary Facilities
01-5000 Temporary Protection, Hoarding, Barricades 28,400 SF $0.85 $24,140 HIGH
01-5010 Temporary Power / Utilities 22 wks $850 $18,700 MED
01-5020 Dumpster, Debris Removal — Public-Building Protocol 22 wks $1,100 $24,200 HIGH
01-7500 Final Cleaning, Punch, Turnover 28,400 SF $0.30 $8,520 HIGH
Division 01 Subtotal $218,810

Division 02 — Existing Conditions / Demolition

CSI Code Description Qty Unit Unit Cost Total Conf.
02-4100 Selective Demolition — Partitions, Millwork, Flooring 28,400 SF $4.20 $119,280 HIGH
02-4200 Ceiling Demolition (tile, grid, clouds) 28,400 SF $1.85 $52,540 HIGH
02-8200 Hazardous Material Abatement Allowance (ACM survey complete) 1 LS $22,000 $22,000 MED
Division 02 Subtotal $193,820

Divisions 06 / 09 — Framing, Insulation & Interior Finishes

CSI Code Description Qty Unit Unit Cost Total Conf.
Light Gauge Steel Framing
06-1000 LGS Partition Framing — Open Office Zones 3,200 LF $18.50 $59,200 HIGH
06-1010 LGS Partition Framing — Private Offices / Conf Rooms 1,840 LF $22.00 $40,480 HIGH
Drywall, Insulation & Ceilings
09-2100 GWB — 2-ply 5/8" Type X STC Assemblies 18,600 SF $3.40 $63,240 HIGH
09-2110 Batt Insulation (acoustic R-11) 14,200 SF $1.10 $15,620 HIGH
09-5100 Suspended ACT Grid + Tile (open zones) 14,800 SF $5.80 $85,840 HIGH
09-5110 Exposed Structure / Painted Deck 13,600 SF $2.20 $29,920 MED
Flooring & Paint
09-6500 LVP Flooring — Open Office + Corridors 19,800 SF $6.20 $122,760 HIGH
09-6800 Carpet Tile — Private Offices / Conf Rooms 7,400 SF $7.50 $55,500 HIGH
09-6900 Polished Concrete — Reception / Lobby Core 1,200 SF $12.00 $14,400 MED
09-9100 Painting — Walls, Ceilings, Reveals, Accent 28,400 SF $2.80 $79,520 HIGH
Div 06/09 Subtotal $566,480

Division 08 — Openings, Doors & Glazing

CSI Code Description Qty Unit Unit Cost Total Conf.
08-1100 Hollow Metal Doors + HM Frames (3068) 44 EA $1,850 $81,400 HIGH
08-7100 Schlage Commercial Hardware Set (lever, closer, HM) 44 EA $680 $29,920 HIGH
08-4100 Aluminum Storefront System — Conference Room Glazing 1,840 SF $48.00 $88,320 MED
08-8000 Glazing Film / Manifestation 1,840 SF $4.50 $8,280 HIGH
Division 08 Subtotal $207,920

Division 12 — Casework, Millwork & Specialties

CSI Code Description Qty Unit Unit Cost Total Conf.
12-3216 Kitchen / Break Room Casework (3 kitchens, one per floor) 3 EA $28,500 $85,500 MED
12-3220 Reception Millwork + Feature Wall (custom) 1 LS $42,000 $42,000 LOW
10-2800 Toilet Accessories, Signage, Fire Extinguishers 1 LS $18,400 $18,400 HIGH
Div 12 / 10 Subtotal $145,900

Divisions 21–28 — Mechanical, Electrical, Plumbing & Low Voltage

CSI Code Description Qty Unit Unit Cost Total Conf.
Division 21–22 — Fire Suppression & Plumbing
21-1300 Fire Sprinkler System Relocate / Extend 28,400 SF $3.80 $107,920 MED
22-1000 Plumbing — Kitchen Rough-in + Fixtures (3 kitchens) 3 EA $14,200 $42,600 MED
Division 23 — HVAC
23-3100 VAV Boxes / Distribution Ductwork — Open Office 28,400 SF $8.20 $232,880 MED
23-8200 Controls / BAS Integration (tie to base building) 1 LS $38,500 $38,500 LOW
Division 26 — Electrical
26-2000 Power Distribution — Panel Circuits, Devices (one panel/flr) 28,400 SF $9.50 $269,800 MED
26-5000 Lighting — LED Fixtures, Dimmers, Daylight Sensors 28,400 SF $7.20 $204,480 MED
Division 27–28 — Data / Security / AV
27-1500 Structured Cabling — Cat6A, Fiber Backbone, Patch 28,400 SF $4.20 $119,280 MED
28-1300 Access Control — Card Readers, Door Hardware Integration 44 EA $1,200 $52,800 MED
28-2300 AV Rough-in (conferencing, displays; GFE by Owner) 12 EA $1,850 $22,200 HIGH
Div 21–28 Subtotal $1,090,460

Markup & Fee Summary

Division 01 — General Requirements incl. $218,810
Division 02 — Existing Conditions / Demo $193,820
Divisions 06 / 09 — Framing & Finishes $566,480
Division 08 — Openings, Doors & Glazing $207,920
Division 12 / 10 — Casework & Specialties $145,900
Divisions 21–28 — MEP & Low Voltage $1,090,460
Subtotal — Direct Construction Cost $2,423,390
General Conditions (on-site supervision, temp facilities) already incl. in Div 01
Overhead & Profit 7.5% $181,754
Insurance (Builder's Risk + GL) 1.2% $29,081
Payment & Performance Bond 0.85% $20,599
Design Contingency (Level 2 ROM) 5.0% $121,170
GMP ESTIMATE — SULPHUR SPRINGS PUBLIC LIBRARY $2,775,994

Estimating Assumptions & Exclusions